3. Phase 2

Phase 2 consists of property protection works at The Oaks, Pines Cottage and Iron Gate Lodge. This consists of the construction of flood gates, walls and raised drives. The work at The Oaks was completed March 2016, while the the work at Pines Cottage is partially complete (as of May 2016). The work at Iron Gate Lodge is scheduled for June 2016.