Guide Feniton

Show all parts of this guide

5. Phase 4

Phase 4 consists of the installation of the 1050mm diameter pipe. Starting at Metcombe Cottage, the pipe will be installed up to and connected into the railway crossing installed as part pf Phase 3. The pipe will continue north of the railway, across Green lane and into Wells Avenue heading northwards through Warwick Close. The pipe will pass through the corner of the Wainhomes site, into the Parish Council’s play area and head north towards the Youth Centre. It will re-enter the Wainhomes site before travelling north to Station Road and the fields behind Mount View. Tendering for this work will happen in the Summer 2016 with the work starting on site in the Autumn 2016.