East Devon District Council

Cookies information

eastdevon.gov.uk uses cookies to make the site simpler. Find out more about the cookies we use.

Guide Moving and Improving: all you need to know about the office relocation

Show all parts of this guide

6. Project timeline - key dates

It is important to note that these dates remain indicative only as there are a mix of factors outside the control of the council that may create delays in this process. The project will adapt as necessary.

April 2018

  • Relocation to Honiton complete.

December 2017

  • Relocation to refurbished Exmouth Town Hall.

December 2016

  • Cabinet and Council (separately) will take the opportunity to review the Project.  This is known as Gateway 7 which is to note satisfaction of the financial requirements and restrictions of the Final Design, confirmation of Contractors Project Costs, advice regarding Planning Application for EDDC at Heathpark and for Pegasus Life Ltd at Knowle.

October 2016

  • Development Management Committee is expected to determine the planning application by East Devon District Council for Heathpark, Honiton.

September 2016

  • Development Management Committee is expected to determine the planning application by Pegasus Life Ltd for Knowle.

April 2016

November 2015

  • Contractor appointed for Pre-construction Role (part of the 2 stage tendering process).

September 2015

  • Design team Aecom appointed.

July 2015

  • East Devon  exchanges contracts with Pegasus Life Ltd - the developer selected to purchase and develop Knowle. Pegasus specialises in providing retirement and extra care facilities, for which there is huge demand in Sidmouth and the wider area.

March 2015

December 2014

February 2014

September 2013

July 2013

March 2013

March 2012

  • Selection process for relocation project management completed and appointment of Davis Langdon as contracted provider.

July 2011