3. Timetable
A timetable for the review
A CGR must, by statute be concluded within a twelve-month period from the day on which the CGR starts. A CGR starts when the District Council publishes its Terms of Reference and concludes when the District Council publishes the recommendations made in the CGR.
The following is the review timetable:
Action | Timetable | Dates |
Compiling Terms of Reference | October 2021 | |
Terms of Reference report to Cabinet | November 2021 | |
Council approves Terms of Reference | December 2021 | |
Council approves Terms of Reference | January 2022 | |
Stage one – Invite initial submissions | 3 months | 4th February 2022 to 4th May 2022 |
Stage two – Consideration of submissions received and draft proposals prepared | May 2022 | |
Stage three – Draft proposals are published and consultations made | 3 months | June 2022 to August 2022 |
Stage four – Consideration of submissions received and final proposals prepared | September/October 2022 | |
Preparation of Recommendation and approval by Cabinet | November 2022 | |
Preparation of Recommendation and approval by Council | December 2022 | |
Publication of Recommendations | December 2022 | |
Effective date of Order | December 2022 | |
Parish Council elections under new arrangements | May 2023 |