Guide Standard conditions of contract

Show all parts of this guide

32. Assignment and sub-contracting

32.1        The Supplier shall not sub-contract any part of the Contract without the prior written consent of the Buyer. Sub-contracting any part of the Contract shall not relieve the Supplier of any obligation or duty attributable to it under the Contract including these conditions.

 

32.2        Where the Buyer has consented to the placing of sub-contracts, copies of each sub-contract shall be sent by the Supplier to the Buyer immediately it is issued.

 

32.3        The Supplier shall ensure that its sub-Suppliers are informed of these Conditions and required to comply with them at all times.