6. CIL Process

In summary the process is as follows:

Blue = For applicant
Red = For EDDC

Submit CIL Additional Information Form with Full or Reserved Matters application (the completed form is required to make the application valid)

Down Arrow 

  Checking and validating the application

Down Arrow
Submit Assumption of Liability Form and any relevant Exemption Form before determination of planning permission

Down Arrow
Application determined, calculate liability and issue Liability notice to the parties that have assumed liability (and/or landowners if nobody has assumed liability). Liability Notice registered as a local land charge.

Down Arrow
Submit Commencement Notice to inform when development will commence. This is in addition to notifying Building Control on the commencement of works.

Down Arrow
Issue Demand Notice for CIL Payment

Down Arrow
CIL pail in line with payment procedure

Down Arrow
Receipt for payment issued and local land charge removed.